MSBA Board of Directors Meeting, January 27, 2010
PROJECT
Capital Planning Power Point Presentation
A. Invitation to Feasibility Study
- Exhibit C (includes Districts below)
- Boston: Dearborn Middle School
- Burlington: Marshal Simonds Middle School
- Hancock: Hancock Elementary School
- Shawsheen Valley Vocational Technical High School
B. Recommendation for Preferred Schematic Design
- Maynard: Maynard High School
- Somerville: East Somerville Community Elementary School
- Sutton: Sutton Middle School
C. Invitation to Project Budget and Scope – Estimated Total Facilities Grants of $215M
- Ashland: David Mindess Elementary School – Estimated $1.5M
- Carlisle: K-8 School – Estimated $7.0M
- Dartmouth: James Quinn Elementary School – Estimated $650 K
- Grafton: Memorial Senior High School – Estimated $36.5M
- Natick: Natick High School – Estimated $43.1M
- North Attleborough: Joseph Martin Elementary School – Estimated $410 K
- Rockport: Rockport High School – Estimated $480K
- Shrewsbury: Sherwood Middle School – Estimated $24.0M
- Southbridge: Southbridge High School – Estimated $53.7M
- South Shore Regional Vocational Technical High School – Estimated $1.6M
- Tewksbury: Tewksbury High School – Estimated $44.2M
- Whittier Vocational Technical Regional High School – Estimated $2.1M
D. Other Capital Planning Information
- 2010 Needs Survey
- FY2010 SOIs
- Space Standards and Guideline Proposed Revisions
- Project Status Report
FINANCE
- Sales Tax Update
- Year-to-Date Expenditures to Cities, Towns and Regional School Districts
- MSBA 2009 Series A / Series B Bond Issuance Summary
AUDIT
- Audit Program Progress and Status Update
- Audit Program Financial Savings Analysis
- Approval of Final Audits with no appeals, MSBA grants of $34.2 million
- Cambridge Rindge and Latin School, $9.0M
- Silver Lake Regional High School, $25.2M