The following Districts presented on the progress of their proposed projects at the December 14, 2011 MSBA Facilities Assessment Subcommittee Meeting:
Franklin Public Schools
Franklin High School
Current Phase: Model School Program
Owner’s Project Manager: Daedalus Projects, Inc.
Designer: Ai3 Architects
The District, owner’s project manager, and design team presented a brief overview of the process that was undertaken to determine that new construction of an MSBA Model School is the District’s preferred solution. They also provided information regarding the status of the Schematic Design. The Facilities Assessment Subcommittee inquired about the location and utilization of certain programmatic spaces unique to the District’s educational curriculum. The District and design team explained how these spaces help deliver the District’s curriculum. Also, the District explained that it will confirm with the MSBA that site issues raised previously by NEASC are addressed in the proposed project. The MSBA is currently working with the District and will determine an agreed upon solution to recommend to the Board of Directors.
Lexington Public Schools
Estabrook Elementary School
Current Phase: Feasibility Study
Owner’s Project Manager: RFWalsh Collaborative Partners
Designer: DiNisco Design Partnership
The District, owner’s project manager, and design team presented on the progress of the feasibility study. The team briefly presented the options that were explored and then focused on potential layout schemes for new construction options. The District’s proposed preferred solution, which is under final review locally, is for construction of a three story elementary school on the northeast portion of the current site. Following the District’s presentation, the Facilities Assessment Subcommittee expressed concern regarding the size and utilization of the shared project areas at the entrance of the classrooms. Ensuing discussion included how the District intends to use these spaces, how they are being used in other schools, and the District’s commitment to utilizing these areas to deliver its curriculum. The District agreed to provide supporting material regarding utilization of the spaces identified as project areas. The MSBA is currently working with the District and will determine an agreed upon solution to recommend to the Board of Directors.
Lincoln Public Schools
Lincoln K-8 School
Current Phase: Feasibility Study
Owner’s Project Manager: Skanska
Designer: OMR Architects
The District, owner’s project manager, and design team presented on the progress of the feasibility study. The team discussed the work conducted during the feasibility study and presented a variety of addition and renovation options, including the preliminary options, the final evaluation of options, and the District’s preferred solution. The District discussed how its preferred solution supports its educational vision for the school. Following the District’s presentation, the Facilities Assessment Subcommittee raised concerns regarding dissonance between the District’s desired educational goals and the architectural floor layout contained in the District’s submittal. The Subcommittee also raised concerns about the proposed project costs. The District will provide additional materials to address these concerns and MSBA staff will continue to work with the District to better understand the connection between the proposed project and the District’s educational needs. The MSBA will continue working with the District to establish an agreed upon solution to recommend to the Board of Directors.
Essex North Shore Agricultural and Technical High School
Essex North Shore Agricultural and Technical School District
Current Phase: Design Development
Owner’s Project Manager: PMA Construction Services
Designer: Design Partnership of Cambridge
The District, owner’s project manager, and design team provided a status update and spoke about the progress of the design and the efforts undertaken to merge the two existing schools into a single Regional School District. Following the District’s presentation, the Facilities Assessment Subcommittee noted that the District should consider incorporating design concepts from the MSBA’s science classroom/lab guidelines to enhance flexibility with potential programmatic adjustments in the future. The Subcommittee also commended the District’s ongoing collaborative efforts to realize expanded student opportunities and increased operational efficiencies. The Subcommittee encouraged the district to continue to strive for interaction between the academies.
Greenfield High School
Current Phase: Feasibility Study
Designer: Dore & Whittier Architects, Inc.
Lynnfield High School
Current Phase: Feasibility Study
Designer: Edward Rowse Architects
Galvin Middle School
Current Phase: Feasibility Study
Designer: Tappe Associates, Inc.
The Assabet Valley Regional School District presented on the progress of their proposed project at the October 19, 2011 MSBA Facilities Assessment Subcommittee (FAS) meeting:
Assabet Valley Regional Technical School District
Assabet Valley Regional Technical High School
Current Phase: Schematic Design
Owner’s Project Manager: Strategic Building Solutions
Designer: Design Partnership of Cambridge
The District, the Owner’s Project Manager, and Design team presented the progress of the Schematic Design phase. The team discussed the work conducted during the Feasibility Study and presented the necessary areas that will require upgrades. The team found that the building had antiquated systems and science labs, and will need to upgrade to current code and accessibility requirements. The team also discussed the proposed floor plans and cost options. Following the District’s presentation, the Facilities Assessment Subcommittee raised concerns about the level of testing and investigations conducted as part of the Schematic Design. This concern was raised as the Subcommittee would like to better understand the project cost estimates and the contingencies carried in the Schematic Design budget. The Subcommittee also asked that the District revisit the science lab classroom design. It was suggested that the District implement the MSBA’s science lab guidelines. The MSBA is currently working with the District and will determine an agreed upon solution to recommend to the Board of Directors.
The following Districts recently presented on the progress of their proposed projects at the September 14, 2011 MSBA Facilities Assessment Subcommittee Meeting.
North Reading Public School District
North Reading High School
Current Phase: Feasibility Study
Owners Project Manager: PMA Consultants
Designer: Dore & Whittier Architects, Inc.
The District, the Owner’s Project Manager, and Design team presented the three options evaluated during the ongoing Feasibility Study and taking into consideration the conditions and constraints of the existing Middle School and High School sites. The three options include: (1) a new Middle School, (2) a new High School, and (3) existing Middle School renovation and addition for an integrated Middle/High School. The District has indicated that their preferred solution is the Middle/High renovation and addition option. The preferred solution includes the renovation of the existing Middle School and the construction of a new High School wing. Core spaces housed within the new construction will be shared by both the High School and Middle School students. The Designer noted that adding to the existing Middle School will improve traffic flow and increase overall natural day-lighting throughout the building, and that this option will minimize impact to the students during construction. Preliminary cost estimates indicate that this preferred solution is the most cost efficient.
The Facilities Assessment Subcommittee raised concerns about the location of the High School core academic wing in relation to the rest of the building and potential flooding at the athletic fields. The Subcommittee also inquired about cost savings opportunities. The MSBA is currently working with the District and will determine an agreed upon solution to recommend to the MSBA Board of Directors.
Stoneham Public School District
Stoneham Middle School
Current Phase: Feasibility Study
Owners Project Manager: Joslin, Lesser & Associates
Designer: Tappé Associates, Inc.
The District, the Owner’s Project Manager, and Design team presented the options evaluated during the Pre-Feasibility Study and the Feasibility Study. The options were narrowed to three. The three options include: (1) addition to the High School (grades 6-8), (2) addition to the Central School (grades 5-8), and (3) new construction on the Central School Site (grades 6-8). During the Pre-Feasibility Study, the District found that the there are only two potential parcels of land that are suitable for this project; they include the existing Middle School site and the existing High School site. The District noted that the overall enrollment for the district is projected to decline and it will be able to reclaim existing elementary school capacity. This projected decline in enrollment informed the District’s preferred solution which is an addition to the Central School that will include relocating elementary students currently housed in the Central Elementary School and adding the fifth grade students to the Middle School. The Designer stated that the preferred solution will require less construction that the other options, will improve traffic in the morning and afternoon, and is the least costly option.
The Facilities Assessment Subcommittee raised concerns about the science labs and number of classrooms with running water, how the team structure is supported by the proposed program, the long-term usage of the classrooms, and adequate egress from the science labs. The MSBA is currently working with the District and will determine an agreed upon solution to recommend to the MSBA Board of Directors.
Williamsburg Public School District
Anne T. Dunphy Elementary
Current Phase: Feasibility Study
Owners Project Manager: Arcadis
Designer: Drummey Rosane Anderson, Inc.
The District, the Owner’s Project Manager, and Design team presented the options evaluated during the ongoing Feasibility Study. The Designer presented six options that have been evaluated throughout the study. The six options include: (1) modest renovations and code upgrades to the Dunphy Elementary School and the James Elementary School, (2) comprehensive renovations to both the Dunphy Elementary School and the James Elementary School, (3) renovation and addition to the James Elementary School, (4) comprehensive renovation and addition to the Dunphy Elementary School producing a courtyard, (5) comprehensive renovation and addition to the Dunphy Elementary School producing a split-grade scenario, and (6) new construction. The District noted that the preferred solution, consisting of an addition and renovation split-grade scenario at the Anne T. Dunphy School, which combines students from the both the Dunphy Elementary School and the James Elementary School, best supports the District’s educational program and is the most cost effective option according to the preliminary estimates.
The Facilities Assessment Subcommittee raised concerns about the number of classrooms with running water, the specific need for dedicated computer and science classrooms, the lack of resource rooms, and the potential for flooding. The MSBA is currently working with the District and will determine an agreed upon solution to recommend to the MBSA Board of Directors.
The Southwick-Tolland Regional School District recently presented on the progress of their proposed project at the August 24, 2011 MSBA Facilities Assessment Subcommittee Meeting.
Southwick-Tolland Regional School District
Southwick-Tolland Regional High School
Current Phase: Feasibility Study
Owners Project Manager: Strategic Building Solutions
Designer: JCJ Architecture
The District, its Owner’s Project Manager, and Designers discussed conditions at the existing Woodland Elementary School, Powder Mill Middle School, and Southwick-Tolland Regional High School. The team presented study options that were evaluated as part of the ongoing Feasibility Study, the proposed District-wide reconfiguration, and regionalization efforts between the Towns of Southwick, Tolland, and Granville. The team presented its preferred option, which is contingent upon a successful regionalization vote with the Town of Granville. The proposed option includes repairs to the Woodland Elementary School and the Powder Mill Middle School; and an addition and renovation to the High School for a proposed Middle/High School facility. If the vote between the three towns is unsuccessful, the District will proceed with its priority, the High School, for an addition and renovation for a new Middle/High School only.
The Facilities Assessment Subcommittee raised concerns over the lack of day-lighting in the existing High School facility and questioned specific programmatic adjacencies. The MSBA is currently working with the District to determine a final solution for recommendation to the MSBA Board of Directors.
The Wilmington Public School District recently presented on the progress of their proposed project at the July 13, 2011 MSBA Facilities Assessment Subcommittee Meeting.
Wilmington Public School District
Wilmington High School
Current Phase: Feasibility Study
Owners Project Manager: Joslin, Lesser & Associates
Designer: Dore & Whittier Architects, Inc.
The District, the Owner’s Project Manager, and design team discussed the conditions of the existing Wilmington High School and presented study options that were evaluated as part of the ongoing feasibility study. The team presented several options that were initially explored during the study which ranged from various addition and renovation options to multiple versions of new construction on the existing site. New construction options on four possible alternate sites were also explored initially. Through a detailed evaluation of all of the options explored, two options were considered as viable options for further study. The two options include: (1) an addition and renovation to the existing building and (2) construction of a new building on the existing site. The District has indicated that their preferred option is to replace the existing high school with new construction given the current size, condition of the existing facility, and favorable preliminary estimated cost. The design team’s preliminary cost data estimates that a new building will be more cost effective and will reduce the duration of construction.
The Facilities Assessment Subcommittee raised concerns over the proposed square footage in certain areas of the proposed new program, specifically in the art, music, vocational, and auditorium areas. The MSBA is currently working with the District to better understand the programmatic needs of Wilmington High School to determine an agreed upon solution.
The following Districts recently presented on the progress of their proposed projects at the May 11, 2011 MSBA Facilities Assessment Subcommittee (FAS) meeting:
The following District presented on the progress of its proposed project at the April 20, 2011 MSBA Facilities Assessment Subcommittee (FAS) meeting:
Norton Public School District
Norton High School
Current Phase: Feasibility Study
North Adams Public School District
Silvio O. Conte Middle School
Current Phase: Feasibility Study
The following Districts recently presented progress of their projects at the MSBA Facilities Assessment Subcommittee (FAS) meeting: